Utility Distribution System Upgrade Replaces Old Capitol Tunnel

Replacing a Deteriorated Tunnel Network Requires Modern Solutions

view inside old tunnel with pipes running through it

Steam pipes run through an old section of utility tunnel on the University of Iowa campus.

The labyrinth of utility networks running under the streets, homes, and businesses of Iowa City has sections that date to the mid-1800s. Several of these tunnels exist as conduits for steam pipes to heat buildings on the University of Iowa campus. One such passage, known as the Old Capitol tunnel, runs along the east curb line of Madison Street. Stretching from the Universities Power Plant to the Pentecrest, this tunnel is critical to the steam service on the east side of campus. It provides a path for condensate return to the Power Plant and completes a significant east campus steam loop providing operational reliability to the entire campus.

Due to its susceptibility to flooding, a section of the Old Capitol tunnel between Burlington Street and Washington Street had deteriorated to a point that replacement was necessary. An engineering team with Snyder & Associates was brought on board to develop a solution that would meet the needs of a number of end-users. In lieu of dismantling and constructing a new tunnel section, our team developed a plan to replace the tunnel with a series of direct-buried pipes and concrete vaults spaced at appropriate intervals.

Utility Coordination & Streetscape Improvements

In addition to the direct-bury steam/condensate utility replacement, this project also involves a high level of coordination with other university, city, and franchise utilities along the Madison Street corridor. There are numerous locations where the proposed direct-bury replacement piping crosses existing water, chilled water, sanitary sewer, storm sewer, electrical and communication duct banks, and lighting circuits. To coordinate this highly complex environment, 3-D modeling software was used by our engineering team to map the utility structures and plan the necessary relocations as the project progressed.

multi-color 3D modeling of pipe system

3-D modeling software was used to locate and track the multiple utilities in the reconstruction area.

This project also includes a streetscape component aimed at restoring the surface features following the utility construction. The streetscape features include plantings, upgraded sidewalks and crosswalks, and other amenities targeted to the college students, such as convenient bike parking and multiple waste receptacles. Improvements to transit facilities, including bus stops and shelters, as well as safety improvements within the adjacent Seamans Center are also part of the project scope.

A high degree of coordination is necessary to formulate a construction phasing and traffic control plan that accommodates the construction activities while considering the needs of building users, transit mobility, the general public, and other construction projects occurring within the area. This complex, Snyder & Associates-designed project is currently underway with substantial completion targeted for the late summer of 2021.

Client

University of Iowa

Client Type

Project Type

Nathan Carhoff, P.E.

Nathan Carhoff, P.E.

Transportation Engineer

Related Projects

8th Avenue Reconstruction & Mount Vernon Road Rehabilitation – Cedar Rapids, Iowa

The 8th Avenue Reconstruction & Mount Vernon Road Rehabilitation project, designed by Snyder & Associates, represents one of Cedar Rapids’ most significant...

3rd Street Northeast Reconstruction – Belmond, Iowa

Modernizing Infrastructure and Enhancing Connectivity in Belmond To address aging infrastructure and improve overall street conditions, the City of Belmond partnered...

Hickman Road & SE Legacy Pointe / NW 161st Street Intersection Improvements

To support long-term traffic efficiency and corridor consistency along Hickman Road, the cities of Clive and Waukee partnered on a joint project to reconstruct and...
Overlaid pavement on 1st Ave with railroad crossing in the background|Aerial view of Ellis Boulevard and 6th street NW Connector & 1st ave rehabilitation in Cedar Rapids Iowa|Aerial view of Ellis Boulevard and 6th street NW Connector & 1st ave rehabilitation in Cedar Rapids Iowa|Aerial view of Ellis Boulevard and 6th street NW Connector & 1st ave rehabilitation in Cedar Rapids Iowa|Railroad crossing|Roundabouts Streamline Traffic Flow|Cars driving around the roundabout creating efficient traffic flow|1st Ave & 6th Street Intersection facing North Before & After Construction

Ellis Boulevard & 6th Street NW Connector & 1st Avenue Rehabilitation: Cedar Rapids

A planning initiative performed in the community of Cedar Rapids identified a critical need for better connections and smoother traffic flow between the Kingston...
Aerial rendering of the Grand Avenue roadway extension in West Des Moines|Map of National Flood Hazard Layer of the project area|Image of construction taking place for Grand Avenue extension in West Des Moines Iowa with construction workers and cement trucks in the background|Newly poured roadway with road crew working in the background.|Image of construction taking place for grand avenue extension in West Des Moines Iowa|New bridge over Johnson Creek with earthwork still to complete underneath.|View of the Johnson Creek Bridge along Grand Avenue with the new monuments installed on either side.|Custom-designed monuments for the City of West Des Moines

Grand Avenue Extension in West Des Moines Opens Additional Area for Development

To provide access to Microsoft's new data center and open additional area for development in southwest West Des Moines, city leaders contracted with Snyder and...
Roundabout in Anamosa Iowa|Roundabout in Anamosa Iowa|Overview of US 151 Grade Separation and Roundabout in Anamosa Iowa|Roundabout design showcasing lighting and signage in Anamosa Iowa|Man cutting the ribbon for US 151 Grade Separation and Roundabout in Anamosa Iowa||US 151 Grade Separation and Roundabout: Anamosa

US 151 Grade Separation and Roundabout: Anamosa, Iowa

In a strategic move to address safety concerns and bolster regional connectivity, the City of Anamosa required a unique transportation solution to address a regional...
Community members look over public engagement displays at a local event.||Pavilion in Sidney

Comprehensive Neighborhood Revitalization Plan Aims to Lift Sidney Community

Situated just a short drive from Omaha down Interstate 29, Sidney has long been popular with residents and commuters from neighboring cities. However, Sidney has not...
NE 51st Avenue intersection along US 69 reconstruction project.|intersection with traffic lights|Intersection at NE 70th Avenue intersection along the US 69 reconstruction project.|Intersection of NE 60th Avenue near the Polk County Sheriff's Office along US 69 reconstruction.|median under construction|LiDar image of US 69 reconstruction|Snyder & Associates Transportation experts

US 69 Reconstruction: Paving the Way for Future Growth in Ankeny

In the heart of unincorporated Polk County, a bustling two-lane corridor known as US Highway 69 (NE 14th Street) has long been a critical lifeline connecting Des Moines...
This rendering shows several design ideas that would allow food trucks to inhabit the space for community events|Overhead deception showing numerous amenities the design team proposed for the Merrill Alley section of this project|Plans showing the upgrades and improvements to transform 3 alley ways in Fort Dodge

Fort Dodge Alleyways Three-Block Master Plan Enhances Community Space

In the heart of Fort Dodge, tucked away behind the buildings lining Central Avenue between Ninth and 12th Streets, lies the canvas for an ambitious project — the Fort...
newly constructed roadway intersection|Road traffic transitions into roundabout|Improved traffic flow due to new corridor|Snyder & Associates worker surveying roadway construction|group of people attending a ribbon cutting for new roadway|tower terrace roadway map

Tower Terrace Road Upgrades Fill Gap in Northern Connector Initiative

Nearly two decades ago, planners for Linn County and several surrounding communities — including Cedar Rapids, Hiawatha, and Marion — began laying the groundwork for an...

more than 45 years