3-D Modeling Design Technology Increases Efficiencies for Roadway Reconstruction: Interstate 35

Increasing Efficiencies for Interstate Reconstruction Design: Iowa DOT

As part of an on-call design contract, the Iowa Department of Transportation (DOT) tapped Snyder & Associates to complete the final roadway design work for multiple construction contracts on Interstate 35 spanning Polk and Warren Counties. The design covers I-35 beginning south of the Iowa Highway 92 Interchange and extends over 16 miles to the I-35/80/235 Interchange (regionally known as the West Mixmaster) in West Des Moines.

The project included extensive grading and paving work near the Iowa 92 interchange, as well as the design and paving of the roadway approaches to the new northbound and southbound bridges spanning the North River and Badger Creek. In addition, the northbound lanes of I-35 were reconstructed from the Polk/Warren County line to the West Mixmaster.

Pavement Concerns, Roadway Deficiencies, & Design Changes

Initially constructed in 1958, the existing pavement in the project area was some of the oldest in Iowa’s Interstate system and required costly ongoing maintenance. In addition to the poor pavement conditions, specific areas to be addressed were:

  • Two interchanges in Warren County and one in Polk County which had physical and geometric roadway deficiencies.
  • Functionally obsolete and structurally deficient bridges located throughout the corridor. This included overhead bridges at Iowa 92 and County Road G14 which didn’t meet current vertical clearance standards and had been struck by tall vehicles several times.
  • Widening of I-35 from four lanes to six lanes to accommodate increased traffic throughout the corridor. (Some areas will remain a four-lane facility, but can easily be expanded to six lanes as future traffic volume requires.) Expansion to six lanes throughout the entire corridor is anticipated for 2032.
  • Detailed staging and complex traffic control plans were required to maintain safe and efficient traffic flow on I-35 during the construction.
  • Due to plan changes made during years of construction with multiple construction contracts, the original design created by Iowa DOT required numerous updates to better facilitate the project. Snyder & Associates was able to quickly complete these changes to arrive at the final design.

3-D Modeling Technology for Automated Machine Guidance (AMG)

Our team also developed 3-D machine control files. These files were made available to contractors in order to use Automated Machine Guidance (AMG). AMG is a process whereby construction equipment utilizes onboard computers and global positioning system (GPS) technology for horizontal and vertical guidance in real-time.

For certain types of grading work, AMG has the potential to achieve designed grades on the first pass. This results in fewer budgetary impacts and shorter construction timeframes. Other benefits of using AMG include improved quality, better safety for construction workers compared to traditional staking, and more efficient use of already limited resources.

Financial Planning Assistance for Roadway Projects

Prior to Snyder & Associates completing the final project design, the cost of all programmed projects was estimated at less than $100 million. However, because there were projects in the original environmental assessment that had not yet been programmed, that cost was expected to increase. Once all projects were added, the estimated cost exceeded $140 million. Because federal funds were being used for the project, a financial plan reviewed by the Federal Highway Administration (FHWA) was required. This requirement pertains to all projects with an estimated cost between $100 million and $500 million. Snyder & Associates navigated this complex financial planning process for the client in consultation with the FHWA.

The purpose of a financial plan is to ensure financial resources for large projects are identified, available, and properly managed during the life of the project. It’s a comprehensive document designed to reflect the project scope, schedule, cost, and funding. The plan goes far beyond the typical cost estimates prepared by engineers. Progress is tracked over time through annual updates to the initial financial plan. Each annual update reviews and tracks actual dollars spent on each project and anticipated changes to overall project costs over the past fiscal year. This helps to determine if changes to project programming are needed.

While it’s typically only done for large, complex projects, this type of detailed financial planning strategy is useful for smaller projects, as well. Although the financial plan for a small project is less complicated, it’s equally important to track all aspects of the project cost, changes that occur, and anticipated funding sources. In the event of a funding shortfall, Snyder & Associates can assist with the identification of potential funding sources and the preparation of required applications.

Snyder & Associates completed both the final roadway design and financial plan for the reconstruction of Interstate 35 while overcoming several challenges along the way. Snyder & Associates’ flexibility and commitment to doing what is necessary to ensure the success of a project is the foundation of our firm’s dedication to our customers.

Client

Iowa DOT

Client Type

Project Type

Wade Greiman, P.E.

Wade Greiman, P.E.

Transportation Business Unit Leader

Related Projects

Aerial view of a grid of streets in a small town, with fall foliage and a yellow water tower at center.

Iowa Highway 14 Four-to-Three Lane Conversion Improves Safety and Traffic Flow in Knoxville

When the Iowa Department of Transportation identified an opportunity to rehabilitate and resurface Iowa Highway 14 through Knoxville, the project became more than a...

HM Zander Nature Park Shelter Creates New Gathering Space Near Downtown Cross Plains

Situated near Downtown Cross Plains and the scenic Black Earth Creek corridor, the open-air shelter and spectator space at HM Zander Nature Park create a welcoming...

Jasper County Highway F-48 Improvements Strengthen Safety and Connectivity

Jasper County has undertaken a multi-phase improvement program along County Highway F-48, extending from the City of Newton/Lambs Grove area west to the Polk...

Prairie Ridge Sports Complex – Ankeny, IA

Supporting Premier Community Athletics Destination Snyder & Associates has partnered with the City of Ankeny over the years to help shape, improve, and expand...

Memorial Tower Replacement Expands Water Storage Capacity in Council Bluffs

Expanding Capacity for the Future: Council Bluffs Water Works Memorial Tower Replacement Council Bluffs Water Works (CBWW) is replacing its long-serving Memorial Tower...

Site Design & Sustainability Drive Sun Prairie Library Expansion

Snyder & Associates played a central role in the planning and site design for the Sun Prairie Public Library Expansion and Renovation Project. This $26 million...

8th Avenue Reconstruction & Mount Vernon Road Rehabilitation – Cedar Rapids, Iowa

Grand Place Award in the Transportation Category for the 2026 Engineering Excellence Awards Competition for ACEC Iowa The 8th Avenue Reconstruction & Mount Vernon...

3rd Street Northeast Reconstruction – Belmond, Iowa

Modernizing Infrastructure and Enhancing Connectivity in Belmond To address aging infrastructure and improve overall street conditions, the City of Belmond partnered...

Enhancing Access at Atwater Park, Village of Shorewood, Wisconsin

Perched atop a bluff 100 feet above the shores of Lake Michigan, Atwater Park is one of Shorewood’s most iconic civic spaces. Serving as a passive park, community...

Hickman Road & SE Legacy Pointe / NW 161st Street Intersection Improvements

To support long-term traffic efficiency and corridor consistency along Hickman Road, the cities of Clive and Waukee partnered on a joint project to reconstruct and...

more than 45 years

Serving Clients Around the Country