Design of Unit Train Service Addition to Industrial Site: Global Agricultural Products Corporation

Plans to Accommodate Unit Train Shipping Service to Improve Transport

The project site for a Global Agricultural Products Corporation was served by the Union Pacific Railroad (UP) through manifest train service but didn’t possess the rail assets needed to accommodate unit trains. To keep trains running proficiently, many industrial corporations consider unit train shipping service because it’s the most efficient form of land transportation. Unit trains can be between 65 cars in length and 200 cars (or more), varying on the location and railroad. All cars in the freight train carry the same type of commodity, from origin to destination. Also important to note, the locomotives pulling the train will typically stay connected throughout the entire journey promoting time-saving.

View of railroad train and tracks

The client required space for 110 cars with 48 hour turnaround time on equipment and a drive-in, drive-out design.

The UP required space for 110 cars with 48 hour turnaround time on equipment and a drive-in, drive-out design. Unfortunately, the existing yard and loading equipment were unable to accommodate these requirements. Snyder & Associates served as the lead designer and initially provided assistance to verify the overall feasibility of accommodating unit train service. After determining that required improvements were possible and UP could provide service, the design of upgrades was initiated.

The owner operates an established, busy yard facility that was required to remain in service 24 hours a day, 365 days a year during construction. Working with the owner, designs were developed to enable continued operation and accommodation of the addition of unit trains. To handle unit trains, extensive changes in standard facility operating procedures were required. We assisted the owner to develop operating sequences that drove design parameters. The design included extensive grading and construction of approximately 14,000 feet of additional track, turnouts, grade crossings, and connections to the existing yard track. Numerous utilities were present in the construction area. Coordination of utility relocation and accommodation was conducted throughout the project design.

Space was limited, so creative site design was critical. A new track was designed to run parallel to the existing UP corridor with geometry designed to accommodate large road locomotives and switching equipment. The owner hasn’t released the project for construction yet.

Client

Confidential

Client Type

Project Type

Darin Jacobs, P.E.

Darin Jacobs, P.E.

Water Resources Work Group Leader

Related Projects

Aerial view of a grid of streets in a small town, with fall foliage and a yellow water tower at center.

Iowa Highway 14 Four-to-Three Lane Conversion Improves Safety and Traffic Flow in Knoxville

When the Iowa Department of Transportation identified an opportunity to rehabilitate and resurface Iowa Highway 14 through Knoxville, the project became more than a...

HM Zander Nature Park Shelter Creates New Gathering Space Near Downtown Cross Plains

Situated near Downtown Cross Plains and the scenic Black Earth Creek corridor, the open-air shelter and spectator space at HM Zander Nature Park create a welcoming...

Jasper County Highway F-48 Improvements Strengthen Safety and Connectivity

Jasper County has undertaken a multi-phase improvement program along County Highway F-48, extending from the City of Newton/Lambs Grove area west to the Polk...

Prairie Ridge Sports Complex – Ankeny, IA

Supporting Premier Community Athletics Destination Snyder & Associates has partnered with the City of Ankeny over the years to help shape, improve, and expand...

Memorial Tower Replacement Expands Water Storage Capacity in Council Bluffs

Expanding Capacity for the Future: Council Bluffs Water Works Memorial Tower Replacement Council Bluffs Water Works (CBWW) is replacing its long-serving Memorial Tower...

Site Design & Sustainability Drive Sun Prairie Library Expansion

Snyder & Associates played a central role in the planning and site design for the Sun Prairie Public Library Expansion and Renovation Project. This $26 million...

8th Avenue Reconstruction & Mount Vernon Road Rehabilitation – Cedar Rapids, Iowa

Grand Place Award in the Transportation Category for the 2026 Engineering Excellence Awards Competition for ACEC Iowa The 8th Avenue Reconstruction & Mount Vernon...

3rd Street Northeast Reconstruction – Belmond, Iowa

Modernizing Infrastructure and Enhancing Connectivity in Belmond To address aging infrastructure and improve overall street conditions, the City of Belmond partnered...

Enhancing Access at Atwater Park, Village of Shorewood, Wisconsin

Perched atop a bluff 100 feet above the shores of Lake Michigan, Atwater Park is one of Shorewood’s most iconic civic spaces. Serving as a passive park, community...

Hickman Road & SE Legacy Pointe / NW 161st Street Intersection Improvements

To support long-term traffic efficiency and corridor consistency along Hickman Road, the cities of Clive and Waukee partnered on a joint project to reconstruct and...

more than 45 years

Serving Clients Around the Country