Extensive Traffic Study Leads to Roadway Improvements

Large stone neighborhood sign

The Pinnacle Prairie neighborhood along Greenhill Road continues to expand.

Cedar Falls has experienced a steady population and commercial growth over the past three decades. Along with that growth comes the correlating issue of heavier traffic and more congested roadways. In Cedar Falls, one of these pain points is along the Greenhill Road corridor. Greenhill Road is a four-lane, undivided arterial that serves as a main east/west thoroughfare along the southern edge of Cedar Falls. In addition to new commercial development in the area, one other factor that has led to the increased traffic volumes is the continued expansion of the Pinnacle Prairie development to the south of Greenhill Road.

Snyder & Associates was contracted by the city to perform a traffic study on the 2.7-mile section of Greenhill Road, from the intersection with Hudson Road in the west to the Cedar Heights Drive intersection in the east. This comprehensive study encompassed eleven public intersections that currently consist of a mix of signalized and two-way STOP controlled (TWSC) intersections.

Signalized Intersections vs. Roundabouts and Multimodal Considerations

People gather for public engagement presentation

In conjunction with Cedar Falls staff, Snyder & Associates hosted numerous public sessions.

The goal of the study was to provide the city with short- and long-term plans for upgrades and improvements to the Greenhill Road corridor. The study’s challenges included:

This study was accomplished through data collection, a safety performance review, and current and forecasted traffic volumes and intersection operations. A life cycle cost analysis was also performed to compare the alternatives for a traffic signal or roundabout at the intersections requiring traffic control beyond TWSC. In addition, three public feedback sessions were held to allow interested citizens the opportunity to express opinions regarding the corridor plan.

Cost-Saving Recommendations

Renderings of roundabout plans

Roundabouts were recommended at multiple intersections along the corridor.

The immediate, short-term recommendations offered to the city were to update vehicle and pedestrian clearance timings at signals, fill in the sidewalk gaps along the south side of Greenhill Road and improve signage and pavement markings at several intersection approach locations.

For long-term consideration, it was recommended to add signals at two current TWSC intersections and to widen roadways for turn lanes at four of the intersections. Also, it was recommended to convert five signalized intersections to roundabouts, with immediate priority being given to the Cedar Heights Drive and South Main Street intersections. After being approved by the city council, these two roundabout conversions are slated to begin construction in 2020 and 2021, respectively. While upfront costs will be higher than traditional signalized intersections, our firm’s study determined the roundabout conversions will result in considerable cost savings over the lifespan of the project, as well as improved safety, efficiency, and traffic flow.

Client

City of Cedar Falls

Client Type

Project Type

Mark Perington, P.E., PTOE

Mark Perington, P.E., PTOE

Traffic Work Group Leader

Related Projects

Aerial view of a grid of streets in a small town, with fall foliage and a yellow water tower at center.

Iowa Highway 14 Four-to-Three Lane Conversion Improves Safety and Traffic Flow in Knoxville

When the Iowa Department of Transportation identified an opportunity to rehabilitate and resurface Iowa Highway 14 through Knoxville, the project became more than a...

HM Zander Nature Park Shelter Creates New Gathering Space Near Downtown Cross Plains

Situated near Downtown Cross Plains and the scenic Black Earth Creek corridor, the open-air shelter and spectator space at HM Zander Nature Park create a welcoming...

Jasper County Highway F-48 Improvements Strengthen Safety and Connectivity

Jasper County has undertaken a multi-phase improvement program along County Highway F-48, extending from the City of Newton/Lambs Grove area west to the Polk...

Prairie Ridge Sports Complex – Ankeny, IA

Supporting Premier Community Athletics Destination Snyder & Associates has partnered with the City of Ankeny over the years to help shape, improve, and expand...

Memorial Tower Replacement Expands Water Storage Capacity in Council Bluffs

Expanding Capacity for the Future: Council Bluffs Water Works Memorial Tower Replacement Council Bluffs Water Works (CBWW) is replacing its long-serving Memorial Tower...

Site Design & Sustainability Drive Sun Prairie Library Expansion

Snyder & Associates played a central role in the planning and site design for the Sun Prairie Public Library Expansion and Renovation Project. This $26 million...

8th Avenue Reconstruction & Mount Vernon Road Rehabilitation – Cedar Rapids, Iowa

Grand Place Award in the Transportation Category for the 2026 Engineering Excellence Awards Competition for ACEC Iowa The 8th Avenue Reconstruction & Mount Vernon...

3rd Street Northeast Reconstruction – Belmond, Iowa

Modernizing Infrastructure and Enhancing Connectivity in Belmond To address aging infrastructure and improve overall street conditions, the City of Belmond partnered...

Enhancing Access at Atwater Park, Village of Shorewood, Wisconsin

Perched atop a bluff 100 feet above the shores of Lake Michigan, Atwater Park is one of Shorewood’s most iconic civic spaces. Serving as a passive park, community...

Hickman Road & SE Legacy Pointe / NW 161st Street Intersection Improvements

To support long-term traffic efficiency and corridor consistency along Hickman Road, the cities of Clive and Waukee partnered on a joint project to reconstruct and...