2727 SW Snyder Blvd, Ankeny, IA 50023

1 (888) 964-2020



Navigation

Back to Projects | Project Categories: Stormwater | Wastewater

Leachate Disposal Solution for Des Moines County Landfill & the City of West Burlington

For many years, the Des Moines County Landfill relied on the traditional yet costly method of trucking excess water that percolated through the landfill, commonly known as landfill leachate, off-site whenever its storage lagoons became full. Over the years, however, expenses related to leachate disposal at wastewater treatment plants increased, placing an untenable economic burden on the waste management facility. As a potential solution, the Des Moines County Regional Solid Waste Commission (SWC) proposed a solution for the permanent leachate disposal at the West Burlington sewer system. Viewed as an option to lower taxpayer costs within the City of West Burlington, both parties consented to the agreement, and plans for the project were launched.

Managing Dual Client Representation for Leachate Disposal Solution

The Snyder & Associates team was hired to represent the city’s and the landfill’s needs throughout this project. When providing services for multiple parties, clear agreements and constant communication are vital to satisfactorily satisfy all needs. Since the city leaders agreed to construct the project for the landfill, we helped both clients navigate the process to enter a Chapter 28E agreement under the Iowa Code. This agreement allows cities to contract with other governmental units—in this case, the county landfill. Additionally, to ensure the partnership was protected in the future, we prepared a substantial industrial use agreement between our clients for monitoring and reporting the characteristics of the leachate. Per this agreement, the landfill cannot exceed an average of 58,000 gallons of leachate disposal per day and has a maximum limit of 80 gallons per minute. The industrial use agreement also outlines specific parameters for contaminants such as cadmium, copper, lead, nickel, silver, BTEX, and benzene to ensure nothing harmful is conveyed to the West Burlington treatment plant.

Leachate Conveyance Route Options & Project Construction

With agreements in place, our team began preparing preliminary studies for various pumping alternatives and piping routes to establish the most economical yet agreeable solution for the conveyance needs. Alignment A offered a shorter route with fewer grade transitions but would require multiple permits to construct a utility within the state highway right-of-way. Alignment B featured a longer route but avoided private property and easement acquisitions. Despite the higher upfront construction cost, alignment B resulted in the cheaper option in the long run. The group unanimously selected alignment B, and the final designs were moved forward.

waste management force main construction

The force main will connect the landfill to West Burlington’s wastewater distribution system for leachate disposal.

For this project, we started by constructing the lift station at the landfill. The station’s location was pre-determined as the site had a previously placed utility hole that allowed pumping and the necessary access to power. This lift station was constructed as a submerged wet well lift station typical for transmitting wastewater flows. Our team then transitioned the construction phase to installing piping sections, adding over 12,000 linear feet of 4-inch diameter, high-density polyethylene (HDPE) piping. This material was selected because it can be installed in longer sections than PVC. Since the project pathway runs through the public right-of-way, most of the construction could be done via open-cut installation. However, the pipe intersects an active railroad at one location, and trenchless installation was applied to limit disruptions. In a client request, we added pipe access cleanouts every 500 feet along the segments. While this is typically unorthodox for force main because of the pressure pipe, access was needed along this long expanse of pipe for special cleaning due to the nature of the waste. This mutually beneficial waste management project reduced landfill expenses, and the lower costs ultimately trickle back to the taxpayers. The Snyder & Associates team was proud to bring the city and the county’s needs to the contractor to facilitate the construction of a project that minimized environmental impacts, avoided wastewater treatment plant operation interruptions, and mitigated the disturbance to nearby neighborhoods.

Client

City of West Burlington & Des Moines County

Client Type

Project Type

Lindsay Beaman, P.E.

Lindsay Beaman, P.E.

Cedar Rapids Business Unit Leader

recent projects & completed jobs

Related Projects

Water

Memorial Tower Replacement Expands Water Storage Capacity in Council Bluffs

Expanding Capacity for the Future: Council Bluffs Water Works Memorial Tower Replacement Council Bluffs Water Works (CBWW) is replacing its long-serving Memorial Tower with a new 1.0-million-gallon elevated storage tank, increasing capacity fivefold over the existing 200,000-gallon tower built in […]

Water

Radial Collector Wells Strengthen Water Supply for Atchison, Kansas

Snyder & Associates helped Atchison develop new radial collector wells, improving raw water capacity, reliability, and long-term drinking water resilience.

Aerial rendering of the Grand Avenue roadway extension in West Des Moines|Map of National Flood Hazard Layer of the project area|Image of construction taking place for Grand Avenue extension in West Des Moines Iowa with construction workers and cement trucks in the background|Newly poured roadway with road crew working in the background.|Image of construction taking place for grand avenue extension in West Des Moines Iowa|New bridge over Johnson Creek with earthwork still to complete underneath.|View of the Johnson Creek Bridge along Grand Avenue with the new monuments installed on either side.|Custom-designed monuments for the City of West Des Moines

Structural, Transportation, Water

Grand Avenue Extension in West Des Moines Opens Additional Area for Development

To provide access to Microsoft's new data center and open additional area for development in southwest West Des Moines, city leaders contracted with Snyder and Associates and our structural engineering subsidiary, Shuck-Britson, to design the roadway extension of Grand Avenue, […]

more than 45 years

Serving Clients Around the Country