2727 SW Snyder Blvd, Ankeny, IA 50023

1 (888) 964-2020



Navigation

Eureka Bridge Rehabilitation Improves Historic Structure

Bridge Upgrades Preserve Iconic Structure

Originally constructed in 1912 with only minor modifications in the intervening years, the Eureka Bridge in central Iowa has been listed on the National Register of Historic Places since 1992 as part of the original Lincoln Highway. Spanning the North Raccoon River just west of the City of Jefferson, this historically significant structure consisted of a five-span, concrete arch bridge with closed-spandrel, earth-filled arches.

Eureka Bridge in Green County before Rehab was done

Before rehabilitation efforts, the bridge was too narrow to meet current highway standards.

Greene County officials were faced with the decision of either replacing this bridge or finding an engineering firm capable of designing rehabilitation measures that would preserve the integrity of the structure while meeting current bridge and highway design standards. After a difficult decision-making process, the Greene County Board of Supervisors and Greene County Engineer chose Shuck-Britson to design the bridge upgrades and parent company, Snyder & Associates to design the roadway approach.

Bridge Rehabilitation Preserves Historic Charm

The primary concern with the existing bridge was the narrow deck that no longer met the minimum requirements for a highway bridge. Our design team opted to widen the bridge’s deck to the south by extending the existing abutments and piers. This was accomplished by driving long steel pilings deep into the earth to extend the original pilings. These pilings were then able to support the new abutments, piers, and the bridge’s superstructure. The south spandrel wall and concrete rail were constructed to replicate the original construction. Widening the bridge deck to the south also alleviated certain road alignment and right-of-way issues.

earth fill being removed from eureka bridge during rehab

Earth fill was removed from the bridge to be replaced by concrete transverse walls.

Our team’s extensive engineering analysis also focused on the earth-filled superstructure of the original bridge. This analysis determined that an alternate deck support system would increase the live load capacity of the bridge. As a result, the rehabilitation project removed the fill and the concrete deck that it supported and added concrete transverse walls to support a new deck. The earth-fill removed from the bridge was able to be repurposed on the west bank of the river where it formed roadway access to a county park.

The balustrade-design poured concrete guardrails on both sides of the bridge deck were of particular concern for maintaining the bridge’s appearance. Because the deck was widened to the south, the north side of the bridge was left unchanged and the entire north spandrel wall and guardrail were protected and left in place. For the south guardrail, the team decided to replicate the bridge’s original panel-designed, poured concrete guardrail. To comply with highway crash standards, new “transparent” steel traffic rails were built to protect the historic concrete rails according to current design load and geometry requirements. These two-foot-high guardrails were designed so as not to interfere with the exterior view of the bridge.

Roadway Conditions Improved with Additional Modifications

Designing the bridge went hand-in-hand with an analysis of roadway conditions. The road needed to be brought up to current design standards and several alignment adjustments were analyzed within the existing roadway constraints to devise a solution to this challenge. This analysis resulted in the modification of roadway curves, the bridge’s increased width, and the addition of the steel guardrails.

All planning, design, and construction were coordinated by the Shuck-Britson and Snyder & Associates design teams with the Iowa Department of Transportation (DOT), the State Historical Society of Iowa, and Greene County officials. This rehabilitation, while preserving a vanishing piece of Iowa history, will now continue to serve motorists for decades to come.

Learn more about the rich history of the Eureka Bridge.

Client

Greene County

Client Type

Project Type

Craig German, P.E.

Craig German, P.E.

Structures Work Group Leader

Related Projects

8th Avenue Reconstruction & Mount Vernon Road Rehabilitation – Cedar Rapids, Iowa

The 8th Avenue Reconstruction & Mount Vernon Road Rehabilitation project, designed by Snyder & Associates, represents one of Cedar Rapids’ most significant...

3rd Street Northeast Reconstruction – Belmond, Iowa

Modernizing Infrastructure and Enhancing Connectivity in Belmond To address aging infrastructure and improve overall street conditions, the City of Belmond partnered...

Hickman Road & SE Legacy Pointe / NW 161st Street Intersection Improvements

To support long-term traffic efficiency and corridor consistency along Hickman Road, the cities of Clive and Waukee partnered on a joint project to reconstruct and...
Aerial rendering of the Grand Avenue roadway extension in West Des Moines|Map of National Flood Hazard Layer of the project area|Image of construction taking place for Grand Avenue extension in West Des Moines Iowa with construction workers and cement trucks in the background|Newly poured roadway with road crew working in the background.|Image of construction taking place for grand avenue extension in West Des Moines Iowa|New bridge over Johnson Creek with earthwork still to complete underneath.|View of the Johnson Creek Bridge along Grand Avenue with the new monuments installed on either side.|Custom-designed monuments for the City of West Des Moines

Grand Avenue Extension in West Des Moines Opens Additional Area for Development

To provide access to Microsoft's new data center and open additional area for development in southwest West Des Moines, city leaders contracted with Snyder and...
A man running on trail underneath bridge|Creek bank underneath bridge|Map of the new Clear Creek Trail alignment around the Interstate 80/380 interchange|Workers install one of the bridges over Clear Creek|Decorative Concrete castings for Clear Creek Trail Connection|Clear Creek Trail connection bridge|Trail underneath bridge in Coralville Iowa

Clear Creek Trail Connection Fills Critical Multi-Modal Gap: Coralville, Iowa

The Clear Creek Trail project has emerged as a significant addition to the ongoing efforts to enhance connectivity and recreational opportunities in Johnson County....
Overlaid pavement on 1st Ave with railroad crossing in the background|Aerial view of Ellis Boulevard and 6th street NW Connector & 1st ave rehabilitation in Cedar Rapids Iowa|Aerial view of Ellis Boulevard and 6th street NW Connector & 1st ave rehabilitation in Cedar Rapids Iowa|Aerial view of Ellis Boulevard and 6th street NW Connector & 1st ave rehabilitation in Cedar Rapids Iowa|Railroad crossing|Roundabouts Streamline Traffic Flow|Cars driving around the roundabout creating efficient traffic flow|1st Ave & 6th Street Intersection facing North Before & After Construction

Ellis Boulevard & 6th Street NW Connector & 1st Avenue Rehabilitation: Cedar Rapids

A planning initiative performed in the community of Cedar Rapids identified a critical need for better connections and smoother traffic flow between the Kingston...
Roundabout in Anamosa Iowa|Roundabout in Anamosa Iowa|Overview of US 151 Grade Separation and Roundabout in Anamosa Iowa|Roundabout design showcasing lighting and signage in Anamosa Iowa|Man cutting the ribbon for US 151 Grade Separation and Roundabout in Anamosa Iowa||US 151 Grade Separation and Roundabout: Anamosa

US 151 Grade Separation and Roundabout: Anamosa, Iowa

In a strategic move to address safety concerns and bolster regional connectivity, the City of Anamosa required a unique transportation solution to address a regional...
NE 51st Avenue intersection along US 69 reconstruction project.|intersection with traffic lights|Intersection at NE 70th Avenue intersection along the US 69 reconstruction project.|Intersection of NE 60th Avenue near the Polk County Sheriff's Office along US 69 reconstruction.|median under construction|LiDar image of US 69 reconstruction|Snyder & Associates Transportation experts

US 69 Reconstruction: Paving the Way for Future Growth in Ankeny

In the heart of unincorporated Polk County, a bustling two-lane corridor known as US Highway 69 (NE 14th Street) has long been a critical lifeline connecting Des Moines...
newly constructed roadway intersection|Road traffic transitions into roundabout|Improved traffic flow due to new corridor|Snyder & Associates worker surveying roadway construction|group of people attending a ribbon cutting for new roadway|tower terrace roadway map

Tower Terrace Road Upgrades Fill Gap in Northern Connector Initiative

Nearly two decades ago, planners for Linn County and several surrounding communities — including Cedar Rapids, Hiawatha, and Marion — began laying the groundwork for an...
|||Aerial rendering of Hickman and Interstate 35/80 diverging diamond interchange.||Street level rendering of Hickman and Interstate 35/80 diverging diamond interchange.|||Rendering of pedestrian tunnel underneath Interstate 35/80 at Hickman Road diverging diamond interchange.|Bridge abutments design treatment underneath Interstate 35/80 diverging diamond interchange bridge.|||Median treatment rendering underneath Interstate 35/80 diverging diamond interchange bridge.|two pedestrian bridges over the interstate onramps

Progress on the Interstate 35/80 & U.S. 6 Diverging Diamond Interchange Upgrade

The exponential growth of communities, particularly in the western suburbs of Des Moines, has been nothing short of remarkable. The population of Waukee, for example,...

more than 45 years

Serving Clients Around the Country

DB+