Street Flooding Leads to Storm Sewer & Roadway Improvements: Fort Dodge

2024 Engineering Excellence Awards, Honor Award Winner in the Special Projects Category awarded by the American Council of Engineering Companies (ACEC) of Iowa

Flood Mitigation Efforts Implemented to Tackle Decades-Old Stormwater Drainage Problems

Until recently, business owners in the Crossroads Mall area of Fort Dodge were all too familiar with the significant stormwater drainage problems surrounding this retail-heavy, east-side location. A combination of inadequately sized sewer lines and massive amounts of concrete meant water from heavy rainfall had no place to go. This led to flooded roadways and countless instances of stalled vehicles during downpours. For years, city public works crews had to set up portable pumps to remove water from as many as 23 manhole locations during rainstorms.

Our experts were tasked with developing stormwater improvements to mitigate common flooding.

In 2013, the city tasked Snyder & Associates with developing a plan to put an end to these all-too-common flood events in the east region. The resultant East Region Storm Sewer plan put forward would lead to a multi-phase project that would eliminate the almost constant flooding in the area. Integrated into the plan was a design for a safer, more streamlined approach to travel lanes along the busy 1st Avenue South corridor. For aesthetic improvements, plans for decorative street lighting along the corridor were created, as well as plans to remove overhead utilities in the area.

Multi-Phase Project Adds Detention Basins & Larger Sewer Pipes to Improve Drainage Issues

The primary need established by the Snyder & Associates design team was the creation of several regional stormwater detention basins in the area. Detention basins are simply graded depressions in the ground that provide a drainage point for stormwater. The water that drains into the basins is then slowly released over time through a dedicated outlet. Phase one of the project included the construction of a detention basin on the north side of 1st Avenue South, below Veteran’s Bridge. The creation of the basin is just one part of the solution, however. Having an adequate capacity to move stormwater to the basins is also critical. To that end, larger storm sewer pipes were installed along the corridor. These pipes were appropriately sized to meet the needs during heavier rainfall events. Pump station improvements were also made to ration the amount of stormwater coming out of the basin into the smaller storm sewers downstream. Before work commenced on the basin and storm pipes along 1st Avenue South, many of the overhead utilities in the area were buried. MidAmerican Energy worked with the city to install conduit and duct banks from Veteran’s Bridge to approximately 850 ft. east of South 29th Street. Once the underground utilities were installed and activated the overhead utilities were removed.

Roadway Configuration Changes Lead to Better Access Management

Stormwater outlet

Storm sewer pipes and outlets were appropriately sized to meet the needs during heavier rainfall events.

Phase one also included further roadway reconstruction of 1st Avenue South, as well as a section of South 25th Street along the west side of Crossroads Mall. This construction included improvements to lane configurations and better access management for several businesses along the corridor. The lane improvements included the reduction of several four-lane, undivided configurations into two-lane roads with a center, two-way left-turn lane. This process is commonly referred to as a “road diet.” This style of lane alignment is designed to calm traffic, reduce crashes, and provide additional space between vehicles and pedestrians without widening existing roadways.

Additional Construction Phases Help Alleviate Public Interruptions

The next several construction phases included similar improvements along the roadways around Crossroads Mall. By dividing the project into smaller phases, public interruptions were kept to a minimum. This also allowed for the construction of another large detention basin in the region to provide a place for stormwater drainage before the new sewer pipes were put in place.

Complex Financial Planning Assistance

This near $15 million project required procuring project funds from multiple sources outside of normal city funding. These funding sources included the Iowa Department of Transportation, which provided money through the Traffic Safety Improvement Program (TSIP). These funds are available for traffic safety improvements on any public roads under county, city, or state jurisdiction. Iowa Clean Air Attainment Program (ICAAP) funds were also procured since the roadway improvements would result in reduced transportation-related emissions. An additional $1.5 million from the federal government was obtained for the reconstruction of the intersection at 1st Avenue South and South 29th Street. Working side by side with community leaders, the Snyder & Associates team strategized this complex financial plan to complete the sewer and roadway reconstruction project. Our assistance included the identification and application for the program funds. This extensive project is being recognized as having solved the periodic flooding issues of the Fort Dodge east region district, as well as having created a more welcoming streetscape environment through the many roadway upgrades.

Client

City of Fort Dodge

Client Type

Project Type

Wade Greiman, P.E.

Wade Greiman, P.E.

Transportation Business Unit Leader

Related Projects

Aerial view of a grid of streets in a small town, with fall foliage and a yellow water tower at center.

Iowa Highway 14 Four-to-Three Lane Conversion Improves Safety and Traffic Flow in Knoxville

When the Iowa Department of Transportation identified an opportunity to rehabilitate and resurface Iowa Highway 14 through Knoxville, the project became more than a...

HM Zander Nature Park Shelter Creates New Gathering Space Near Downtown Cross Plains

Situated near Downtown Cross Plains and the scenic Black Earth Creek corridor, the open-air shelter and spectator space at HM Zander Nature Park create a welcoming...

Jasper County Highway F-48 Improvements Strengthen Safety and Connectivity

Jasper County has undertaken a multi-phase improvement program along County Highway F-48, extending from the City of Newton/Lambs Grove area west to the Polk...

Prairie Ridge Sports Complex – Ankeny, IA

Supporting Premier Community Athletics Destination Snyder & Associates has partnered with the City of Ankeny over the years to help shape, improve, and expand...

Memorial Tower Replacement Expands Water Storage Capacity in Council Bluffs

Expanding Capacity for the Future: Council Bluffs Water Works Memorial Tower Replacement Council Bluffs Water Works (CBWW) is replacing its long-serving Memorial Tower...

Site Design & Sustainability Drive Sun Prairie Library Expansion

Snyder & Associates played a central role in the planning and site design for the Sun Prairie Public Library Expansion and Renovation Project. This $26 million...

8th Avenue Reconstruction & Mount Vernon Road Rehabilitation – Cedar Rapids, Iowa

Grand Place Award in the Transportation Category for the 2026 Engineering Excellence Awards Competition for ACEC Iowa The 8th Avenue Reconstruction & Mount Vernon...

3rd Street Northeast Reconstruction – Belmond, Iowa

Modernizing Infrastructure and Enhancing Connectivity in Belmond To address aging infrastructure and improve overall street conditions, the City of Belmond partnered...

Enhancing Access at Atwater Park, Village of Shorewood, Wisconsin

Perched atop a bluff 100 feet above the shores of Lake Michigan, Atwater Park is one of Shorewood’s most iconic civic spaces. Serving as a passive park, community...

Hickman Road & SE Legacy Pointe / NW 161st Street Intersection Improvements

To support long-term traffic efficiency and corridor consistency along Hickman Road, the cities of Clive and Waukee partnered on a joint project to reconstruct and...

more than 45 years

Serving Clients Around the Country