2727 SW Snyder Blvd, Ankeny, IA 50023

1 (888) 964-2020



Navigation

Back to Projects | Project Categories: Wastewater

Wastewater System Analysis & Planning: Cedar Falls, Iowa

Engineering Achievement Award, ACEC-IA, 2019

Community Growth Prompts New Wastewater System Needs

Steady population growth and an expanding commercial base led to sewer system capacity issues in Cedar Falls, Iowa. In 2006, the City asked Snyder & Associates to examine the Bluff Street Lift Station and the sanitary sewer collection system that drained to it.

The evaluation studied over 17 square miles of City tributary leading to the Bluff Street Lift Station. As part of the study, we conducted flow monitoring and field inspection activities to locate, quantify, and evaluate rainfall-induced inflow and infiltration entering the City’s wastewater collection system. Our analysis led to the development of the Bluff Street Lift Station Drainage Area Wastewater Master Plan, which analyzed existing infrastructure and provided recommendations for improvements.

Key areas of focus during our comprehensive analysis included:

new bluff creek lift station building

The Bluff Street Lift Station underwent revisions to increase its pumping capacity.

  • Existing sanitary capacity
  • Likelihood for future growth
  • Ability of the current system to handle the existing and future sewer flows

Recommendations that resulted from the Master Plan were to:

  • Increase the capacity of the City’s Bluff Street Lift Station
  • Expand the capacity of the City’s trunk sewer
  • Reduce inflow and infiltration through improvements to the existing sanitary sewer conveyance system

Planning & Analysis to Improve Sanitary Sewer Conveyance System

After the development of the Wastewater Master Plan and construction of the 17th Street Lift Station in 2013, the City proceeded with plans to improve the Dry Run Creek sanitary trunk sewer conveyance system. The project goal was to increase the City’s sewage capacity to account for long-term needs as community growth continues. We provided planning, design, and construction management services to develop the new sanitary sewer conveyance system that would meet the City’s goal.

We began by developing a conceptual facility plan for the site through careful planning and continuous client involvement and interaction. Secondary client goals were developed and incorporated into the plan that included:

  • Improving system reliability
  • Reducing inflow and infiltration (I/I)
  • Limiting disruptions to the public and environment
  • Identifying the most economical path of conveyance

Ground-Penetrating Radar Assists with Sanitary Sewer Alignment & Conflict Identification

While planning the proposed sanitary sewer alignment, several challenges were encountered. One of the most significant challenges was the need to pass under the 18th Street Bridge east of Main Street in Cedar Falls. After requesting as-built plans for 18th Street and reviewing the site’s history, it became evident that the bridge had been rebuilt sometime after Highway 58 was constructed. We were concerned that the old bridge abutment was lying in conflict with the proposed sanitary sewer.

To investigate below the surface and determine if the old bridge abutment was in conflict without having a destructive impact, we used ground-penetrating radar.

The use of ground-penetrating radar is common in the archaeological field, where it is used for locating artifacts, but it’s not widely used for civil engineering purposes. However, for this application, it was an appropriate solution because of its non-destructive nature. The results of the radar test indicated a large mass near the elevation of the proposed sanitary sewer. Using this information, appropriate bid items were put in place in the project documents. During construction, the contractor encountered a portion of the old bridge abutment and was able to remove it without additional compensation due to the information the radar provided.

Increasing Sewer System Capacity to Accommodate Future Needs

This project is an example of a complete sanitary sewer design that incorporates future planning needs and encourages sustainable development. The project was designed to increase the sewage capacity from 15.9 million gallons per day (MGD) to 51.5 MGD. It serves as the primary conveyance system for 17.4 square miles of service area with a projected design life of 100 years and predicted ultimate build-out.

The project encompassed replacing approximately 6,850 linear feet of existing sewer and increasing capacity by 55 percent. An additional 1,350 linear feet of cured-in-place plastic lining pipe rehabilitation was included, in conjunction with seven cast-in-place in-situ manhole rehabilitations. Replacement pipe ranged from 36-inches to 54-inches in size and included approximately 900 linear feet of trenchless sanitary sewer installation beneath Highway 58, University Avenue, and Main Street in Cedar Falls. The pipe material was selected was centrifugally cast fiberglass reinforced polymer mortar pipe (CCFRPMP) and ductile iron pipe (DIP).

Continuous Collaboration Helps Project Team Exceed Goals

The project encountered several obstacles during construction including utility conflicts, limited construction space, shallow bedrock, high groundwater levels, bypassing large sewage flows, multiple creek crossings, Department of Transportation (DOT) right-of-way (ROW) crossings, and long trenchless pipe installations.

Continuous collaboration, regular discussions, and design meetings were needed to ensure all components of the facility worked seamlessly together.  The design team worked very well together and delivered a final product that exceeded client goals.

The new facility exceeded the project goals by conveying flows to the 17th Street Lift Station approximately 30 days ahead of schedule without major service disruption to the public. Additionally, the project was let at approximately 20 percent under the preliminary budget for complete construction and was built under the contractor’s bid values.

Snyder and Associates was responsible for managing the entire project and ensuring a complete, efficient and functioning wastewater design that met all project goals. Over the course of the project, we conducted field surveys, temporary flow monitoring and quantification, flow data analysis, 75 manhole inspections, CCTV inspection and cost-effective analysis for over 12,800 linear feet of sanitary sewer, and hydraulic modeling of the wastewater collection system. The team of professionals that was assembled to complete the project included civil, environmental, geotechnical, and structural engineers.

This project exemplifies the high level of project success and satisfaction obtainable when the owner, designer, and contractor collaborate closely throughout all project stages.

Due to many factors including the innovative application of techniques, project value, complexity, and sustainable design considerations, it was selected to receive a 2019 Engineering Achievement Award from the ACEC-IA.

Client

City of Cedar Falls

Client Type

Project Type

Lindsay Beaman, P.E.

Lindsay Beaman, P.E.

Cedar Rapids Business Unit Leader

Related Projects

exposed siphon at omaha papio creek|drone map of the Papio Creek in Omaha NE|papio creek stream

Safeguarding Critical Infrastructure and Water Resources: Omaha’s “Papio” Creek

In March 2019, the City of Omaha faced a significant threat to its critical infrastructure under West Papillion Creek (known to locals as Papio Creek). A disastrous...
Leachate Disposal Lift Station at Des Moines County Landfill|excavator digging trench for sewer force main|Leachate Disposal Submersible Wet Well Lift Station|Leachate Disposal Construction of Force Main|Leachate Disposal Wastewater force main Cleanout

Leachate Disposal Solution for Des Moines County Landfill & the City of West Burlington

For many years, the Des Moines County Landfill relied on the traditional yet costly method of trucking excess water that percolated through the landfill, commonly known...
Slater wastewater treatment greenhouse at sunset|Wastewater lagoon with aeration bubbles|Greenhouse and settling pond|Aerial view of large lagoon cell drained for construction|Slater's new greenhouse for wastewater treatment|Inside Slater greenhouse with empty cells|Inside of slater wastewater treatment plant with algae belts.|Slater wastewater treatment plant ribbon cutting|visitors walk inside the new Slater greenhouse and view RAB belts|aerated lagoon at the slater wastewater treatment plant|RAB belts at the Slater wastewater treatment plant

Slater Incorporates Algae to Treat Community Wastewater

2025 Engineering Excellence Grand Prize Award in Water & Wastewater Category, awarded by the American Council of Engineering Companies (ACEC) of Iowa I 2025 Grand...
blue and red map of sewer system service area|corroded manhole|lime green map of pleasant hill sewer system and neighboring communities

Growth in Pleasant Hill Leads to Sanitary Sewer System Review

Snyder & Associates was tasked with conducting a Sanitary Sewer System Review, identifying long-term system and infrastructure upgrades.

square concrete new lift station|above ground section of vertical screen|large machine used to bore holes and make way for pipe|trenchless construction|lead tubing being placed before pipe|concrete tube that will eventually house pumps|square concrete new lift station

Lift Station Upgrades Eliminate Backups & Increase Efficiencies: Anamosa

Anamosa 2nd Street Wastewater Lift Station Improvements As community leaders in mature communities know, the need for new and more efficient wastewater systems is a...
large rectangle wastewater lagoon pond|snowy fields with school in distant background||large dirt hole during lagoon construction|concrete walls of the lagoons lift station placed in the ground

Starmont High School’s Wastewater Dilemma Requires Speedy Solution

Thanks to positive client relationships and word-of-mouth recommendations, Snyder & Associates was hired to find a viable wastewater solution for a high...
aerial view of two large blue lagoons and operation buildings||waterside view of lagoon and gravel shores|metal walkway between two lagoons. One is rough and one is smooth.||

West Burlington’s Wastewater Treatment Plant Upgraded to Meet Current NPDES Requirements

Snyder & Associates wastewater engineers were enlisted to develop a plan for remodeling and expanding West Burlington’s existing wastewater treatment...
car sprays water while driving through a large puddle||car sprays water while driving through a large puddle|view of downtown skyscrapers at then end of a main street|satellite map with project area outlined in red|construction work in a deep trench

Des Moines’ Sewer Separation Initiative Prevents Flooding, Backups & Overflows

Antiquated Stormwater & Wastewater System Fails to Meet New Standards When the City of Des Moines wastewater system was initially constructed, viable methods for...
Inside of the Disinfection-Flow Equalization Tank.|Inside of the SBR tank looking at the aeration piping system.|Inside of treatment tank looking at piping

Custom Wastewater Treatment Solutions for Growing Industrial Client

Working with this industrial client for over ten years, Snyder & Associates continues to provide the most cost-effective, environmentally-sound, and...
cement building with blue roof|grey wall of electrical pannels|multiple pumps in cement room|three oval motors in a row|looking down on multi-level facility floors|

New Pump Station Expands St. Joseph’s Eastside Sewer System Reach

The City of St. Joseph selected Snyder & Associates to replace the outdated, undersized Easton Road pump station with a newly designed wastewater facility in an...

more than 45 years

Serving Clients Around the Country

DB+